From Sketch to Safe Structure: Why Temporary Works Design Briefs Matter
- info3187438
- Jun 1
- 5 min read
A concept is not a design
Event structures often begin with a simple idea. It might be a sketch on paper, a supplier concept, a 3D render, or a previous build that someone wants to adapt for a new site.
That is completely normal. Most creative event projects start that way.
The problem starts when the concept is treated as though it is already a design.
A sketch can show what something might look like, but it does not prove:
How the structure is supported
How loads transfer safely to the ground
Whether the structure is stable in wind
Whether the ground can take the load
Whether modifications have weakened the structure
Whether people can safely access or use it
Whether an independent design check is required
This is where temporary works planning becomes important.

A recent example: an elevated DJ booth between container bars
A recent project involved a proposed elevated DJ booth positioned above and between modified shipping container bar units. Visually, the idea worked well.
Two lower container bars.
A raised DJ booth in the middle.
A clear opening beneath.
A strong event look.
But from a safety and temporary works point of view, there were some major questions that had to be answered before anyone could safely build it.
The lower containers were not standard, unmodified shipping containers. They had been altered to create open serving fronts for bar use.
That matters. Once a container is cut, opened up or modified, it cannot automatically be assumed to retain the same structural capacity as an original container. The side walls, rails, posts and panels may all contribute to the container’s strength and stiffness.
So the key question became:
"Can the modified lower container bars safely support the elevated DJ booth above them?"
That is not something to guess. It needs formal temporary works design.
Temporary Works Design Brief - What needed to be considered?
The temporary works design brief identified the key issues that needed to be assessed by a competent engineer.
These included:
Load transfer from the upper DJ booth into the lower containers
Whether loads could be transferred through container corner posts or primary frame members
Whether spreader beams, grillage, bracing or independent supports were required
Whether the open bar fronts reduced the strength or stiffness of the lower containers
Whether the DJ booth could safely span between the two lower containers
How the upper booth would be fixed, locked or restrained
Wind loading, uplift, sliding and overturning
Ground bearing and pad sizes
Maximum occupancy and equipment loading
Rear stair access and edge protection
Whether people could safely pass beneath the structure once installed
Inspection and handover before use
The point was not to produce the structural design ourselves. The point was to create a clear, structured brief so the appointed engineer knew exactly what needed to be assessed.
Why the design brief matters
A temporary works design brief sits between the concept and the formal design.
It helps turn “We want to build this” into “This is what needs to be designed, checked and controlled before it can be built.”
A good design brief helps:
Define the structure and intended use
Identify key design risks early
Confirm what information the client and installer must provide
Set out what the engineer needs to assess
Clarify what drawings, calculations and design outputs are required
Identify whether an independent design check is needed
Create an action tracker so responsibilities do not get lost
Without that step, clients can end up with a dangerous gap between the creative concept and the actual design responsibility.

Temporary works responsibility can easily fall into a grey area
Many event organisers and suppliers do not have a Temporary Works Coordinator already appointed. That does not mean the responsibility disappears.
If a temporary structure is being built, especially one that is elevated, bespoke, modified or used around the public, someone needs to make sure the design process is properly controlled.
That includes asking:
Who is appointing the temporary works designer?
Who is checking the design?
Has the design considered build, live use and de-rig?
Has the structure been inspected before use?
Are the design assumptions valid for the actual site?
Has the installer built it exactly as designed?
A design brief does not replace the engineer or Temporary Works Coordinator, but it helps the client understand what needs to happen next. It also helps prevent the common mistake of relying on “we have done something similar before”.
Similar is not the same as designed.
Why a Category 3 design check may be needed
For higher-risk temporary works, an independent design check may be required.
In this type of arrangement, a Category 3 independent design check may be appropriate because the structure may be:
Elevated
Bespoke or non-standard
Built from modified structures
Positioned above or near public areas
Subject to wind uplift and lateral loading
Reliant on accurate positioning and load transfer
Used within a live event environment
A Category 3 check means the design is reviewed by a competent engineer who is independent from the original designer.
That check should review the calculations, drawings, load path, container suitability, connections, ground bearing, wind loading, build sequence, operational limits and handover requirements.
For the client, this provides a much stronger level of assurance before the structure is installed or used.
A sketch is the start, not the finish
Creative concepts are important. Events need bold ideas, good visuals and practical supplier input.
But when those ideas involve temporary structures, especially elevated platforms, containers, stages, scaffold, viewing decks or public-facing installations, the concept must be taken through a proper design process.
That means:
Define the concept
Identify the risks
Produce a temporary works design brief
Appoint a competent designer
Complete the structural design
Arrange the required design check
Install to the approved design
Inspect and hand over before use
Skipping those steps can leave clients exposed.
How Orakul Safety can help
At Orakul Safety, we help clients bridge the gap between concept and formal design.
We help clients understand what needs to be designed, checked and controlled before a temporary structure is installed.
This can include:
Reviewing early concepts
Identifying temporary works risks
Preparing temporary works design briefs
Creating engineer’s consideration documents
Building action trackers for client, installer, designer and checker responsibilities
Supporting the appointment process for designers and design checkers
Reviewing whether design outputs answer the right safety questions
Helping clients manage build, inspection and handover requirements
This is especially useful for event organisers, venues, production companies and suppliers who have a creative concept but do not yet have a clear temporary works process in place.
Final thought
If you are planning an event structure, container build, viewing platform, temporary stage, scaffold feature or bespoke installation, do not wait until build day to ask whether it is safe.
Get the concept reviewed early.
Produce a clear temporary works design brief.
Make sure the right designer and checker are appointed.
Then build from a design, not from a sketch.
Need help with temporary works planning?
Orakul Safety supports events, venues and SMEs with practical health and safety, temporary works planning and design brief support. If you have a concept that needs turning into a safe, buildable design process, get in touch.
ORAKUL Safety Ltd.
Wisdom in action
_edited.png)



Comments